US 17/Eastport Intersection
Better Jacksonville Plan, BJP-2
Status Report is for October 30, 2007

DESCRIPTION:
This is a BJP Intersection Improvement Program project.
STATUS:
Current Activity: PLANNING PHASE: Final report
has been reviewed and accepted by the FDOT.
Funding: Revised BJP Program allocation is
$0.59 million. Funding is currently provided for only the planning
phase.
Schedule: The planning phase was completed
in the May 2007.
DBE/MBE DBE participation conformed with City
policies.
SIGNIFICANT ISSUES: Additional funding for
future phases - design, right-of-way and construction id needed.
PROJECT MANAGER: Hamid Tabassian
CONTACT:
Wendy Morrow, (904) 598-8733
email - wmorrow@jtafla.com