HOT NEWS

ROUTE 51 ON DETOUR
CSX repair work to the railroad crossing on Edgewood at Beaver will continue July 27-31. Both lanes of Edgewood will be closed between Cassat Ave. and Beaver St. The only bus route that will be affected is Route 51, which will be on detour. No bus stops will be missed. However, heavy traffic delays are expected.

SR 9B - 9A to US 1


Better Jacksonville Plan, BJP-2
Status Report is for May 2013

This is a rendered view of SR 9B - SR 9A to US 1 project. For more information call 630-3181.

DESCRIPTION: Provide a new multi-laned limited access roadway link between SR-9A and US-1 near Bayard.

STATUS
Current Activity: The project was advertised on October 5, 2009. Construction began in the Spring of 2010.

Funding: This project is funded through the American Recovery and Reinvestment Act (ARRA), with a maximum cost of $82.4 million.

Schedule: This project is to be completed using the Design/Build method.  Construction began in the Spring of 2010 and has a duration of 900 days.

DBE/MBE: DBE participation will conform with FDOT policies.

SIGNIFICANT ISSUES: None

PROJECT MANAGER: Florida Department of Transportation (FDOT)

CONTACT:
Sandra Mancil
FDOT Public Information
Email:  sdmancil@pbsj.com

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Special Accommodations

Special accommodations such as Braille and large print of all JTA printed documents are available upon request. Contact Customer Service at (904) 630-3100 with your request. Please allow 7-10 days for processing.

Traffic and Transit Info

For information on Traffic reports from 511 click here