July 6 Route Changes

Several route changes and schedule adjustments are planned, starting on Monday, July 6. See an overview in our News & Hot Topics section below.

Matthews Bridge/Arlington Expressway


Better Jacksonville Plan, BJP-2
Status Report is for November 2012

This is a rendered view of Mathews Bridge project. For more information call 630-3181.

DESCRIPTION: Planning - FDOT is conducting a Project Development and Environmental (PD&E) Study.

STATUS
Current Activity: Selection of the recommended alternative is ongoing. Additional information is available at
http://www.mathewsbridge.com/.

Funding: The revised BJP Program provides $3.3 million for the PD&E Study.

Schedule: The PD&E Study schedule is being revised to accommodate additional documentation on the signaficance of the Mathews Bridge.

DBE/MBE: DBE participation will conform with FDOT policies.

SIGNIFICANT ISSUES: Eastern terminus of project at Southside Blvd. and the future depressed areas of Arlington Expressway at Mill Creek Road. There is no funding identified for future phases. Provision of transit corridor.

PROJECT MANAGER: Florida Department of Transportation (FDOT)

CONTACT:
Wendy Morrow, (904) 598-8733