SR 9B - US1 to I-95


Better Jacksonville Plan, BJP-2
Status Report is for May 2013

This is a rendered view of SR 9B - US 1 to I-95 project. For more information call  630-3181.

 

DESCRIPTION: Project includes partial interchange with I-95, an interchange with Philips Highway and a bridge over the FEC railroad tracks.

STATUS
Current Activity: DESIGN PHASE: FDOT has completed 90% design.  The project will be let as a single Design-Build-Finance contract, which will complete the connection from Philips Highway (US-1) to I-95.

Funding: FDOT has 100% of the funding for final design and right-of-way acquisition.  Although the BJP-SPP Program allocates $15 million to this project, BJP funding is not available to support that allocation.  

Schedule:
The Design-Build-Finance team is scheduled to be selected in July 2012.  The team will complete project design, construct the facility and finance the construction.  The Department will reimburse the contractor when the project appears in our Work Program in FY2014/2015.

DBE/MBE: DBE participation will conform with FDOT policies.

SIGNIFICANT ISSUES:
None.

PROJECT MANAGER: Florida Department of Transportation (FDOT)

CONTACT:
Wendy Morrow, (904) 598-8733



Additional Information

All Projects
Development Projects
Mass Transit Projects
Planning Projects
Roadway Projects
Archived Projects


Traffic and Transit Info

For information on Traffic reports from 511
click here

Title VI Program Policy


Program Policy
Title VI Complaint Form
Title VI Policy Statement


Special Accommodations

Special accommodations such as Braille and large print of all JTA printed documents are available upon request.

Contact Customer Service at (904) 630-3100 with your request. Please allow 7-10 days for processing.